We finally finished the steel portion of Building 10 yesterday, Aug 20. It was topped off by a galvanized railing on the front of the building, which will frame out the front parapet walls on the balcony above the retail area.
The next phase is the concrete deck on the second floor. We were able to pour the back portion two weeks ago, and start some of the apartments in the rear:
Meanwhile, the framers keep going. As we poured more concrete, we were able to start more apartments. Then Today, Aug 20, we poured the rest of the main deck. We still have the balconies and porches to pour, but we are clear to continue with verticle contruction of the 2nd, 3rd, and fourth floor of apartments now. Now we will really see results!